Palm Beach State Logo
HOME | JOBS | FAQs | CONTACT US | PEOPLE FINDER
 

Workshop for QEP Development
QEP Action Plan Guidelines
QEP Action Plans Submitted by Committees
Timelines and Due Dates
Templates and Links
Admissions/Registration Committee
Curriculum & Class Scheduling Committee
Distance Learning Committee
Faculty Development Committee
Financial Aid Committee
Human Resources Committee
Information Technology Committee
Recruitment Committee
Student Engagement Committee
Home > Academic Services > Committees > QEP Implementation > QEP Action Plan Guidelines
QEP Action Plan Guidelines

The Action plans to be submitted on or before January 19, 2007 should:

  • State the problem identified in the original QEP
  • State the desired outcome of the QEP
  • Committee's solution

You must state these three things briefly in the template is located at this link: http://www.palmbeachstate.edu/documents/academic_services/QEP_implemention_plan.doc along with the action steps.

The “solution” should be the action plan to implement steps to get to the desired outcome in a three year or less timeframe. The plan should be detailed and clearly outline the steps needed to make the desired outcome happen.

Consider the following example:

Problem: During a hurricane, a tree limb causes a large hole in your roof, causing a serious leak.

Desired outcome: A repaired roof that does not leak

Solution: Action plan to repair the roof. Your “mapping” of the steps to get to the solution is the action plan. In thinking about this problem, there are two general routes: finding a contractor to do the work for you, or actually doing the work yourself. These two approaches should result in the same outcome (hopefully!) but each would require an entirely different action plan and have different costs and timelines.

Detail is very important – this is a possible action plan for fixing the roof, if you were doing the work yourself:

Step

Action

Budget

Timeline

1

Assess damage

??

1 day

2

Buy materials

??

1 day

3

Fix roof

??

1 day

The above plan is not sufficiently detailed to have an accurate assessment of cost or actual time.

Consider this revised plan:

Step

Action

Budget

Timeline

1

Examine roof outside and inside and document damage

NA

1 Day

2

Make detailed materials list for tools/supplies needed

NA

1 Day

3

Assess if you have the tools/materials for the job, make list of tools/materials needed for purchase

NA

1 Day

4

Compare prices materials/tools at Home Depot/Lowe’s

NA

2 Days

5

Purchase materials and tools needed

$1000

1 Day

6

Remove damaged roofing

NA

3 Days

7

Arrange for pickup of damaged roofing materials

$200

1 Day

8

Begin reconstructing wood portions of roof

NA

2 Days

9

Replace tarpaper and shingles

NA

2 Days

10

Test roof for possible leaks

NA

1 Day

11

Beg a contractor to properly fix roof

$2000

1 week

12

Apologize to spouse and take out for dinner

$100

1 day

You can also think about the action plan as being “door to door” directions to get you to your destination – all the turns and roads you need to take to get you where you are going.

 